Grade I insulation installation is mandatory for NGBS compliance. The 2020 NGBS specifically states that "Insulation installation other than Grade I is not permitted" and devotes an entire page to the batt insulation installation criteria to ensure that it is done correctly. Yet, this green building practice, which is seemingly so simple, is by far the most common practice requiring corrective action as identified by Verifiers and has singularly thwarted more buildings from earning NGBS Green certification than any other specific green practice.

The question before Home Innovation is can continuous exterior insulation compensate for cavity insulation that is less than Grade I? Home Innovation says yes and will allow continuous exterior insulation to provide an efficiency backstop for buildings that present Grade II insulation installation, if the Verifier can demonstrate that the combination of CI and batt insulation provides an equivalent or better R-value to what the NGBS requires. 

In contrast to batt insulation, continuous exterior insulation (CI) is easier to install correctly because cutting the insulation to fit in-between studs and around plumbing and electrical is unnecessary. Instead, the material can be cut so that it fits tightly together and is then fixed directly to the wall. And for metal framed buildings, continuous exterior insulation can address thermal bridging at the structural components of building assemblies improving the insulation's impact on energy efficiency. 

Download the Detailed Interpretation

Terms of Use | Privacy Policy

© 2025. Home Innovation Research Labs. All rights reserved. This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Website Design & Development by JET Advertising.